Determine the schedule variance cost variance SPI CPI and CSI for a project that has an actual cost at month

Question

Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month

12 of $90,000, a scheduled cost of $100,000 and an earned value of $120,000.

Project Management